I have battled through the wind, rain and frost but have thoroughly enjoyed this mammoth greenhouse.

Day 1 start all the boxes laid out ready to go.

End of day 1, all glazing bars rubbered and laid out ready to start the build tomorrow.

End of day 2 part of the frame up.

Day 3, a frosty start, roof bars to fit.

End of day 3 and it’s ready to start glazing.

End of day 4, 36 roof bays glazed and 12 windows fitted.

Inside view of the roof.

Day 5, roof and rest of windows fitted and side glazing commenced.

Day 6, glazing finished and doors x 2 sets hung.

Day 7, auto vents and bar capping to finish off, building complete.